KENILWORTH 1 DER
The Kenilworth 1 DER Project is a natural gas-fired electric generation facility located approximately 7 kilometres northwest of Kitscoty, Alberta in the County of Vermilion River.
The Project has a nameplate capacity of 5 MW and is comprised of two 2.5 MW natural gas-fired high efficiency-low emission industrial engines and electrical switchgear, housed within modular buildings.
The Project connects to ATCO Electric's existing 25 kilovolt (kV) distribution line.
The necessary regulatory approvals are in place for the Project with phase 1 construction commencing on July 17, 2023.
Phase 1 construction was completed on September 8, 2023.
The Project began operating on October 11, 2024.