BRIKER 1 DER
The Briker 1 DER Project is a natural gas-fired electric generation facility located near Paradise Valley, Alberta in the County of Vermilion River.
The Project will have a nameplate capacity of 5 MW and is comprised of two 2.5 MW natural gas-fired high efficiency-low emission industrial engines and electrical switchgear, housed within modular buildings.
The Project connects to ATCO Electric's existing 25 kilovolt (kV) distribution line.

The necessary regulatory approvals are in place for the Project with phase 1 construction commencing September 16, 2024.
Phase 1 construction is expected to be completed in October 2024 with Phase 2 construction commencing in November 2024.
The Project reached commercial operations on
December 14, 2024.